Apparatus In Production

This week your water tank has been installed with option content being installed in the pump house and body. In your next report, you may see progress with option content installation in all areas. Your next scheduled report from Weyauwega will be week ending July 11, 2020

This week your body has been merged with the cab/chassis and pumphouse with the water tank being made ready for installation. In your next report, you may see progress with option content installation in all areas. Your next scheduled report from Weyauwega will be week ending June 27, 2020

This week your cab/chassis and pumphouse were merged while the body has begun assembly. In your next report, you may see the body being merged with the chassis with option content being added in all areas. Your next scheduled report from Weyauwega will be week ending June 13, 2020

This week your cab/chassis, pumphouse, and body were staged outside with little progress. In your next report, you may see the pumphouse and body being merged with the chassis. Your next scheduled report from Weyauwega will be week ending May 30, 2020

This week your cab/chassis continued the prep process, your pumphouse has been painted with trim/harnessing installed, along with the body completing the paint process. In your next report, you may see the pumphouse and body being merged with the chassis. Your next scheduled report from Weyauwega will be week ending May 16, 2020

This week your pumphouse had trim and wiring installed, and your body remained in queue to begin the trim and wiring installation process. Next week your body may begin to have trim and wiring installed. Due to Pierce plant travel restrictions in place due to COVID-19, no pictures were taken of your cab and chassis at Weyauwega. Your next scheduled report from Weyauwega will be the week ending May 2, 2020.

This week your pumphouse completed the paint process and your body remained in queue to begin the trim and wiring installation process. Next week both your pumphouse and body may begin to have trim and wiring installed. Your next scheduled report from Weyauwega will be the week ending April 18, 2020.

This week your pumphouse remained in queue go through the paint process and your body completed the paint process. Next week your pumphouse may go through the paint process and your body may begin the trim and wiring installation process. Your next scheduled report from Weyauwega will be the week ending April 18, 2020.

This week your pumphouse remained in queue go through the paint process and your body began the paint process. Next week your pumphouse may go through the paint process and your body may complete the paint process. Your next scheduled report from Weyauwega will be the week ending April 4, 2020.

This week your cab/chassis continued the prep process, your pumphouse was placed in queue to begin the paint process, and your body completed the fabrication process. Next week your cab/chassis may continue the prep process, your pumphouse may go through the paint process, and your body may begin the paint process. Your next scheduled report from Weyauwega will be the week ending April 4, 2020.

This week your apparatus continued chassis preparations at the Weyauwega facility, your pumphouse structure was fabricated, and your body began the fabrication process. In your next report, your pump may be installed in your pumphouse, and your body may complete the fabrication process. Your next scheduled report from Weyauwega will be the week ending March 21, 2020.

This week your apparatus began chassis preparations at the Weyauwega facility. In your next report your apparatus may continue chassis preparations.

In this report, your cab and chassis remained in a staging area. In your next report, your cab and chassis may begin chassis preparations. Your next scheduled report from Weyauwega will be the week ending February 7, 2020.

Your new Pierce apparatus is now in production. In this report, your cab and chassis arrived from the manufacturer. In your next report, your cab and chassis may begin chassis preparations. Your next scheduled report from Weyauwega will be the week ending January 25, 2020.