Apparatus In Production

This week your apparatus began the testing and certification process. Once done, your apparatus will then continue through the quality process in preparation for your customer acceptance inspection. This is your last scheduled report.

« 2 of 6 »

This week your apparatus completed the final assembly process and was placed in queue to begin the testing process. This process may begin next week.

« 1 of 3 »

Since your last report, your apparatus has begun the final assembly line. This is where the majority of body option content is installed. Next week it may continue this process.

« 1 of 4 »

This week your cab and PUC pump were installed on your chassis. Meanwhile, your body had trim and wiring installed. In your next report, your apparatus may begin the pre-assembly process. This is where your tank and body will be installed on your chassis. Due to the annual Pierce plant summer shut down, your next scheduled report will be week ending July 11, 2020. Thank you - Have a very safe, healthy & happy Independence Day week!

« 1 of 3 »

This week your cab continued the content installation process and your plumbing module was assembled. Next week your cab may complete the content installation process, your chassis may begin to have powertrain components installed, and your body may begin the trim and wiring installation process.

This week your cab began the content installation process, your chassis was assembled, and your body completed the paint process. Next week both your cab and PUC pump may be installed on your chassis while your body may begin the trim and wiring installation process.

This week your cab returned from the protective coating application process and was placed in queue to begin the content installation process. Meanwhile, your body completed the fabrication process and began the paint process. Next week your cab may begin the content installation process and your body may continue the paint process.

This week your cab went off site to have protective coatings applied and was unavailable for photography. Meanwhile, your body continued the fabrication process. Next week your cab may return and may begin the content installation process and your body may continue the fabrication process.

This week your cab continued the paint process and your body began the fabrication process. Next week your cab may continue the paint process and your body may continue the fabrication process.

This week your cab began the paint process. Next week it may continue this process.

Your new Pierce apparatus is now in production. This week your cab completed the fabrication process and was placed in queue to begin the paint process. This may begin next week.