Apparatus In Production

This week your apparatus continued the aerial device testing and calibration process. Once done, your apparatus will then continue through the quality process in preparation for your customer acceptance inspection. This is your last scheduled report.

« 1 of 3 »

This week your apparatus began the aerial device testing and calibration process. This process may continue next week.

« 2 of 2 »

This week your aerial device was installed on your apparatus. Next week your apparatus may begin the aerial device testing and calibration process.

« 1 of 2 »

Since your last report, your apparatus continued the final assembly process and your aerial device arrived and began the aerial device final assembly process. Next week your apparatus may complete the final assembly process and then be placed in a staging area until your aerial device has completed its final assembly process.

« 1 of 2 »

This week your apparatus began the final assembly process. It may continue this process in your next report. Due to the annual Pierce plant summer shut down, your next scheduled report will be week ending July 11, 2020. Thank you - Have a very safe, healthy & happy Independence Day week!

This week your apparatus began the pre-assembly process. This is where your tank and body are installed on your chassis. Next week it may complete this process and be placed in queue to begin the final assembly process. This is where the majority of body option content will be installed.

« 1 of 2 »

This week your apparatus was placed in a staging area while your body remained in queue to begin the trim and wiring installation process. Next week your apparatus may remain in staging until your body has trim and wiring installed and is ready to be placed on your chassis.

« 1 of 2 »

This week your aerial pedestal was installed on your chassis. Next week your apparatus may be placed in a staging area while your body may begin to have trim and wiring installed.

« 1 of 2 »

This week your cab and PUC pump were installed on your chassis and your body completed the paint process. Next week your chassis may be placed in a staging area and remain there until your torque box arrives and is ready for installation.

« 1 of 2 »

This week your cab began to have content installed, your chassis began to have powertrain components installed, and your body began the paint process. Next week your cab may continue the content installation process, and your body may continue the paint process.

This week your cab continued the paint process, your chassis was assembled, and your body completed the fabrication process. Next week your cab may complete the paint process, your chassis may begin to have powertrain components installed, and your body may begin the paint process.

This week your cab continued the paint process and your body continued the fabrication process. Next week your cab may complete the paint process and your body may complete the fabrication process.

This week your cab began the paint process and your body began the fabrication process. Next week your cab may continue the paint process and your body may continue the fabrication process.

Your new Pierce apparatus is now in production. This week your cab began the fabrication process. Next week it may complete this process and be placed in queue to begin the paint process.