Apparatus In Production

This week your apparatus completed testing, graphics and quality. It is now being made ready for final inspection. This is your last scheduled report.

« of 6 »

This week your apparatus has conintued final assembly. In the next report the apparatus may complete with release to testing.

« of 6 »

This week your apparatus has conintued final assembly. In the next report the apparatus may continue with final assembly.

This week your has started final assembly. In the next report the apparatus may continue final assembly.

« of 3 »

This week your body was merged with the chassis. In the next report the apparatus may start begin final assembly.

« of 3 »

This week your cab was merged with the chassis followed by installation of the water pump while the body completed paint. In the next report the chassis may continue final assembly while the body may have plumbing installed and begin initial assembly.

This week your cab has started assembly while the frame was built while the body has started in paint. In the next the cab and frame may continue assembly while the body continues in paint.

This week your cab made progress in paint while body fabrication continued. In the next the cab may complete the paint process while body fabrication may wrap up.

This week your cab started in paint and the body started fabrication. In the next the cab may make progress in paint while the body fabrication may continues.