Apparatus In Production

This week your chassis is offsite for sandblasting. The pumphouse currently is staged for installation while the body is finishing fabrication. In your next report the chassis and pumphouse may be merged while the body begins the paint process. Your next scheduled report from Weyauwega will be week ending October 3, 2020.

This week your chassis has started in preperations for mounting of the pump house and body. The pumphouse currently is staged for installation while the body is finishing fabrication. In your next report the chassis and pumphouse may be merged while the body begins the paint process. Your next scheduled report from Weyauwega will be week ending September 19, 2020.

This week your chassis remained staged. The pumphouse finished the paint process and moved to Weyauwega while the body completed the fabrication process and is also at Weyauwega. In your next report the chassis and pumphouse may remained staged while the body may begin the paint process. Your next scheduled report from Weyauwega will be week ending August 22, 2020.

This week your pumphouse completed the paint process. Next week it may be transferred to Weyauwega. Your next scheduled report from Weyauwega will be week ending August 8, 2020.

This week your pumphouse began the paint process and your body may have completed the fabrication process and may now be in transit to begin the paint process (no photos). Next week your pumphouse may complete the paint process and your body may begin it. Your next scheduled report from Weyauwega will be week ending July 25, 2020.

This week your pump was installed in your pumphouse and your body began the fabrication process. Next week your pumphouse may go through the paint process and your body may continue the fabrication process. Your next scheduled report from Weyauwega will be week ending July 25, 2020.

In this report, your cab/chassis remains staged (no photos) while your pumphouse began the fabrication process. In your next report, your pumphouse may have completed the fabrication process and may begin the paint process. Your next scheduled report from Weyauwega will be week ending July 25, 2020.

Your apparatus refurbishment project has begun at the Weyauwega facility. The original pump house and body have been removed from the cab/chassis assembly. In your next report, the cab/chassis will be staged awaiting the pump house and body fabrication. Your next scheduled report from Weyauwega will be week ending June 13, 2020